Capital Projects for Terrytown

Est. Date
Project Description
4Q/24
to
2Q/25
Carol Sue Right Turn Lane at Behrman Hwy.
Add new concrete right turn lane from southbound Carol Sue to westbound Behrman Hwy. Includes adding new sidewalk on the west side of Carol Sue & improving handicap access at bus stop.
Project No.2017-040-RBP
2Q/25
to
2Q/26
Oakwood Smart Growth – Oakwood Area Sidewalk Enhancements and Wright Avenue Improvements (Terry Pkwy. To Hector Ave.)
Improve the existing sidewalks located around the Oakwood Mall. Improve the intersection at Terry Pkwy & Wright Ave. Provide a crossing on Wright Ave at the Oakwood Mall entrance. Re-stripe Wright Ave to be 1-way on each side of the canal.
Project No. 2017-057A-RBP
3Q24
to
2Q25
Wright & Ruby Lift Station
New Lift Station
Project No. SCIP#3563
1Q25
to
4Q26
Terrytown II Emergency Generator
New Generator at Terrytown II Station
Project No. SCIP#3384
No Longer ListedTerrytown 2 Force Main
Installation of the Terrytown 2 Force Main
Project No. SCIP#3415

All Westbank Road Bond Projects

Parish Wide Sewer Bond Projects

Capital Projects Department